The 100-meter road concreting in Springfield, San Isidro, this city is just one of the countless projects of Mayor Eric C. Codilla’s administration. |
PROJECTS by the administration of Mayor Eric C. Codilla continue to pour in barangays. One of the communities that benefited from these projects is Purok Springfield in San Isidro where a 100-meter road concreting began on Sept. 29 and is expected to be completed within 45 days.
The project is located particularly in Pepito St., named after former Barangay Captain Isidro Pepito who donated the land for the road. Project cost is P750,000. Incumbent Barangay Captain Carlito P. Hermosilla said a phase 2 is now being prepared which will extend the concreting to 200 meters more. The project will benefit 16 households that are thankful no
w that their street will not be muddy when it rains. by Jun Colo
(WLWE issue of Nov. 7-13, 2011)